Schedule of works · Rev B · Issued 12 Aug 2026

Outstanding Works
Extension & Garden

Property: [add address] Contact: [add name & phone] Quotes by: [add date]

The extension is structurally complete. The packages below cover the remaining works — quote on any single package or a combination. Each is listed with current status and the decisions still with us, so you can see exactly what's ready to start.

Sequence of works

  1. 1

    Seal the extension

    WP-02 Board and make the front face watertight, then apply the brick slips

  2. 2

    Get the kitchen working

    WP-03 Gas to hob · drainage connection · underfloor heating manifold   WP-04 Pantry wiring

  3. 3

    Building-regs sign-off

    WP-01 Soakaway, guttering connections and drainage run   WP-04 Compliance sign-off (unblocked once pantry wiring from phase 2 is in)

  4. 4

    Further build-out

    WP-03 Outside taps & non-softened supply   WP-01 IBC tanks   WP-04 Outdoor lights   WP-05 Log burner

WP-01

Groundworks & Drainage

Ready to start

New soakaway serving the garage roof and part of the extension roof, with drainage run back to the house. Building control has approved either a shallow-and-broad or a deep design.

WP-02

Exterior Finishing

Slip type TBC

Front face of the extension to be boarded, finished and made watertight, then faced with brick slips for a complete external finish.

WP-03

Plumbing

Part complete
WP-04

Electrics

Awaiting pantry wiring

Our existing electrician will carry out the building-regs sign-off of the extension. He needs the pantry wiring installed first and is happy for the remaining wiring to be done by others.

WP-05

Log Burner

Quote needed

Supply is by us; we're looking for fitting and installation, including flue work as required.

Decisions still with us

So you know what's confirmed and what isn't — none of these should hold up your quote.